Period for reply
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. The third edition, NEC3 was published in 2005.
Many clauses within the NEC suite of contracts establish a period within which a task must be completed by referring to defined dates such as the ‘completion date’, the ‘defects date’, and so on. Some clauses establish a period within which one of the parties must respond to a communication from the other, such as the period for the submission of quotations for compensation events, acceptance of the programme and so on. However, where no such period has been prescribed, then the ‘period for reply’ applies.
The Engineering Construction Contract (ECC) states that:
‘If this contract requires the project manager, the supervisor, or the contractor to reply to a communication, unless otherwise stated in this contract, he or she replies within the period for reply.’
The period for reply is set out in the contract data part one, completed by the employer, and replies to communications must be made within that period, unless another period is stated in the contract. Where a specific time limit is defined within the contract for a particular reply then this will take precedence over the period for reply.
If the project manager fails to reply to a communication within the period for reply, this may constitute a compensation event. If the contractor fails to reply to a communication, then an adjustment may be made to the next payment reflecting the cost to the employer.
An exception to this is where the project manager and contractor agree to an extension before the reply is due.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Compensation event.
- Contract conditions.
- Defects.
- Delay damages.
- Disallowed cost.
- Extension of time.
- Key dates.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Procurement route.
- Time Risk Allowance TRA.
- Variations.
- Z clauses.
[edit] External references
- ‘The New Engineering Contract: A Legal Commentary’, McINNIS, A., Thomas Telford (2001)
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Comments